Construction issues resolution in Sydney - part 17

It's been a while since  the last post In January 2016 the owner lodged an application to NCAT against owners corporation to fix three major defects: - waterproofing of large windows in the living room and bedroom which led to windows full replacement - bathroom drain fix - planterbox fix The owners corporation didn't come to mediation and tribunal ordered to fix all defects within 2 months (the deadline was 8th July 2016). The owners corporation as usual didn't rush to comply with the order regarding two items: bathroom and planterbox. The windows works started end of April 2016. At the same time owners corporation decided to check whether it's a warranty and original builder should fix the issues. That was also related to the fact that the variation was submitted by the current contractor who started fixing the defect. So the owners corporation stopped all works in the middle and went off for a month to "make decision". The decision was mad...