Skip to main content

Construction issues resolution in Sydney - Part 4


On 09/02/2013 the builder came to inspect the exact same defects they have been aware of since September 2012.

During the inspection the builder verbally agreed to fix majority of those defects, rejected some of them as they believed those were maintenance problems and not the building problem and rejected their liability on some of the defects.
The owners corporation requested a report, which should include a list a of defects and exact dates when those defects would be rectified. The builder verbally agreed with that.

After 10 days - 19/02/2013 - the builder sent an email to the owners corporation and Fair Trading that included the unit numbers and the defects that will be fixed/not fixed.
Some defects were missing from the list and as usual there were no firm dates.

Owners Corporation have responded to that email (including Fair Trading) that the report is not complete.

After three days - 21/02/2013 - the builder sent an email providing the contact details of the person who was going to look after the defects rectification and forwarded a correspondence from that person that someone was possibly coming in the following week to fix some of the defects.
They also requested the evidence that some owners notified them about some of the defects! After four times they have been inspecting those!
No certain dates, no list of defects in the email.
As usual nobody appeared or contacted on the following week.

Owners corporation called Fair Trading on 01/03/2013 and the case has been submitted to the Fair Trading inspectors.

UPDATE:
19/03/2013 Fair Trading inspector called and schedule an on site inspection for 17/04/2013.

To be continued.

Other posts from this story.

Comments

Popular posts from this blog

Energy Business Case - Coal Mine in West Virginia

Situation Coal in Africa: An opportunity is available to invest in a coal mine in West Virginia. The mine’s value is less than in past years because of actual and anticipated restrictions on coal-fired power generation in the United States. However, the mine has a chance to sell its coal on contract to a public utility in West Africa. The utility is working through the World Bank for financing to build a number of coal-fired power plants. If they obtain World Bank financing, then a customer for the coal mine is assured, at least for the duration of the contracts. The power plants will employ the best current technology for burning coal, which exceeds all current air quality standards for the region. However, the power plants will not be designed to attempt carbon capture. The area of Africa the plants will serve suffers from extreme energy poverty, with some of the lowest per capita energy consumption in the world.

Overview of the Region West Africa is the westernmost region …

Energy Market Analysis - Coal Reserves for Decade Ending 2012 and Price Forecast

According to the British Petroleum Statistical Review of World Energy, 2013, global coal reserves declined in the decade ending 2012:

Figure 1. Proved coal reserves.

Proved reserves of coal are generally taken to be those quantities that geological and engineering information indicates with reasonable certainly can be recovered in the future from known deposits under existing economic and operating conditions.

If we look at supply and demand factors in the decline, we can see that:

a) Coal price has grown significantly in the decade ending 20121:


  Figure 2. Prices in US Dollars per tonne.

b) Coal consumption has also grown significantly worldwide2:


Figure 3. Coal consumption by region.

c) The price of substitutes (i.e. Natural Gas) has also grown. Not so in North America though, but if we look at the world trend it is growing3:


Figure 4. Natural gas prices.

Therefore if the rule of supply and demand worked we would see increase in proved reserves for coal, because increase in dem…

Construction issues resolution in Sydney - part 17

It's been a while since the last post In January 2016 the owner lodged an application to NCAT against owners corporation to fix three major defects: - waterproofing of large windows in the living room and bedroom which led to windows full replacement - bathroom drain fix - planterbox fix The owners corporation didn't come to mediation and tribunal ordered to fix all defects within 2 months (the deadline was 8th July 2016). The owners corporation as usual didn't rush to comply with the order regarding two items: bathroom and planterbox. The windows works started end of April 2016. At the same time owners corporation decided to check whether it's a warranty and original builder should fix the issues. That was also related to the fact that the variation was submitted by the current contractor who started fixing the defect. So the owners corporation stopped all works in the middle and went off for a month to "make decision". The decision was made at the end of J…